June 9th - Safety Fencing Up, Chain Link Down, Locates Done.
IMG_1158.jpg
IMG_1159.jpg
IMG_1160.jpg
June 21 - Construction Begins, Out with the Old
IMG_0031.jpg
IMG_0029.jpg
IMG_0028.jpg
June 28 - Construction Continues - more gravel - then it rained!
IMG_0044.jpg
IMG_0043.jpg
IMG_0042.jpg
IMG_0045.jpg
July 6 - Layout of Courts, Posts and Fencing
IMG_0063.jpg
IMG_0064.PNG
IMG_0060.jpg
IMG_0061.jpg
Screen Shot 2023-07-06 at 3.38.53 PM.png
NVZ with be light blue
July 11 - Posts, Posts and more Posts 
IMG_0074.jpg
IMG_0077.jpg
IMG_0076.jpg
IMG_0073.jpg
IMG_0072.jpg
July 25 - Final Grading and Compaction plus Storage Shelves 
Alex and Rod playing in the storage area.
July 26 - Applying Tar and Sand - Ready for the Top??
IMG_0111.jpg
IMG_0109.jpg
IMG_0112.jpg
August 30 - Lights, Fences, Levelling, Mesh, ... then paint!!
IMG_0203.jpg
IMG_1398.jpg
IMG_0205.jpg
7aa8dbc4-c523-450c-9480-72b840773e45.JPG
September 1st - Court Mess is Complete, Interior Fences are going up, then the exterior fence . . . it's getting close!
IMG_0230.jpg
IMG_0228.jpg
IMG_0231.jpg
IMG_0232.jpg
September 14th - Painting is almost Completed!  Three colours: Dark Blue, Light Blue, Green plus the Lines.  Waiting for Posts, Nets and Clean Up!
IMG_0257.jpg
September 19th - So Close!!
IMG_0279.jpg
IMG_0273.jpg
IMG_0276.jpg
IMG_0274.jpg
IMG_0272.jpg
IMG_0283.jpg
IMG_0286.jpg
IMG_0280.jpg
bottom of page